This website has been created to keep residents and local stakeholders informed about the upcoming façade remediation works at Monument Court.
GPF Lewis PLC is overseeing the project and is committed to keeping residents updated throughout the duration of the works. This page will be regularly updated with progress reports, key dates, and answers to common questions.
What to Expect:

Works to Date:
Block A
Scaffold installation is mostly complete including hoist #1 & #2 to enable transit of materials & to facilitate works.
All external envelope removed to North, East & South elevation & in part to West elevation
Installation of new non-combustible wall build up has been completed to the North, East & South elevations & in part to West elevation–ready for finishes to be installed.
Brickwork has been completed from Ground to First Floor on the East elevation & through to the 1st floor also. This will now continue up the building level by level.
Block B
Phase 1 scaffold installation to the West, South& East elevations built to 75% complete
Block D
Works commencing 6th July.
General Notes
Ongoing material receipt & distribution to serve the project requirements.
Upcoming Works
Phase 1 scaffold installation to Block B will continue to the West, South and East elevations to allow for hoist installation and the general progression of the works.
Residents are reminded that all belongings must be removed from balconies and ground floor terraces to enable the works to proceed safely and without obstruction.
Works to Block A will continue with the rebuilding of brickwork to the East elevation, progressing from first floor through to second floor level.
Removal of the brickwork envelope to the Northwest elevation will also continue, followed by the installation of the new non-combustible wall build-up. Works to Block D are scheduled to commence ahead of programme during the week commencing 6 July, with material deliveries, receipt and distribution continuing to support the overall project requirements.


General Notes
Our second inspection by the government appointed Building Safety Regulator is due Thursday 4th June where they will inspect all works to date ensure compliance with the Building Safety Act.
As you are already aware, we had measures in place to prevent use of windows & doors for safety & security reasons, in light of the temperature change & upon review, we have removed these measures for ventilation, but we ask for your cooperation with not accessing your balcony at any time, keep your windows open as needed but do not access onto the scaffold as this is a construction zone.
You should take extra care with children & pets should you open your balcony door do not do so beyond a safe distance. Although you can use your balcony outside of working areas the scaffold is alarmed and any access will result in potential police attendance.
You should contact us to arrange an internal conditions survey to be undertaken before any demolition work begins adjacent to your flat, as we cannot be help responsible if this is not first recorded.

GPF Lewis PLC Company Informaiton
GPF Lewis PLC is a UK-based construction and property services company delivering a range of building, refurbishment and remediation projects across residential and mixed-use developments. The company works closely with clients, residents and stakeholders to deliver projects safely, responsibly and with minimal disruption.
Logistics Overview
The following video outlines our approach to logistics throughout the project:


Comments & Questions
We welcome feedback from residents and local stakeholders and are committed to responding to any comments or concerns in a timely and professional manner.
If you have a comment, query, or wish to raise a concern in relation to the works at Monument Court, please use the contact form below. Submissions will be reviewed by the project team and directed to the appropriate member of staff.